Ningbo Jintang Ocean-crossing Tunnel Project
Φ 14.57m CRCHI Slurry-Shield TBM
Project Year: 2024
Project Overview
Project Summary
Location:
The tunnel is located beneath the Jintang Waterway between Ningbo and Zhoushan.
Total length: 16.18 kilometers.
Significance:
The tunnel is currently the longest underwater high-speed rail tunnel in the world, with the Undersea Tunnel section measuring 11.21 km.
Tunneling Machines:
Two Slurry-Shield TBM, each machine has an excavation diameter of 14.57 meters, a length of 135 meters, and weighs 4,350 tons.
Tunneling Operations:
The “Yongzhou” TBM excavates 4,940 meters from west to east.
The “Dinghai” TBM excavates 6,270 meters from east to west.
Both TBMs will eventually meet under the sea, with a centerline misalignment of no more than 2 cm, even after traversing high water pressure zones and complex geological formations.
Construction Difficulties
Geological condition:
The tunnel primarily passes through soft soils, including silt, silty clay, and fine sand, as well as strongly weathered tuff, tuff breccia, and other rock formations.
The strata are heterogeneous, featuring both soft and hard layers, such as silty clay, gravelly soil, and tuff.
The weakly weathered tuff and tuff have compressive strengths of up to 72 MPa and 165 MPa, respectively.
The project is exposed to risks from tides and typhoons, with high and fast-moving sea waves.
Tunnelling Condition for “Dinghai” TBM:
The maximum water depth in the tunnel's marine section is 39 meters, with a maximum burial depth of 86 meters.
The tunnel will experience a maximum water pressure of approximately 0.84 MPa.
The tunnel has a large excavation diameter, making alignment and construction particularly difficult.
Difficulties in alignment and TBM docking due to complex and heterogeneous geology, as well as the challenges of underwater topography.
Jello-Mud Results for “Dinghai” TBM
Jello-Mud Injection for Shield Protection:
During pressurized entry into the tunnel, Jello-Mud is used to fill the annular space around the shield to form a protective ring around the shield body.
Jello-Mud provided excellent barrier effects and ensures sustained protection, especially during long-duration pressurized entry operations.
The method is particularly effective when there are extended shutdown periods during pressurized entry, as it provides long-lasting shielding.
Pressurized and Normal-Pressure Entry Operations:
In the project, pressurized entry work was carried out at the 171st ring, with a shutdown time of 20 days.
Normal-pressure entry work was done at the 209th ring and 243rd ring, with shutdown durations of 3 days and 4 days, respectively.
Jello-Mud’s highest held-pressure recorded in the slurry chamber at 171st, 209th, and 243rd ring are respectively 4.35 bar, 3.87 bar, and 3.63bar
Theoretical Grouting Calculation:
The theoretical annular gap between the outer diameter of the shield (14,520 mm) and the excavation diameter (14,570 mm) is calculated to be approximately 2.28 m³ of Jello-Mud per meter of the shield.
The project plan specifies that the shield will be wrapped with Jello-Mud to create a 5-meter-wide ring.
Therefore, the total theoretical grouting volume required is 11.4 m³ per meter of tunnel, which is injected through 4 reserved grouting ports located at the top and sides of the shield.
This method ensures a continuous protective barrier around the shield, enhancing structural stability and soil pressure resistance during the tunnelling process.
Illustration of annular protective Jello-Mud ring around the shield